Server Upgrade - Disable Scheduled Tasks
Important: We strongly recommend disabling scheduled tasks before you perform an upgrade. This includes all updates to data content and should be done before you create your pre-upgrade backup. This may involve disabling jobs that are triggered outside of Tableau Server, such as those initiated through REST API-based extract refreshes or using tabcmd.
Run the following procedure to disable all scheduled extract refreshes, flows, and subscriptions.
-
Sign in to the Tableau Server Admin Area as the Tableau Server administrator.
-
Go to the server-wide Schedules page:
- On a Tableau Server where only a single (Default) site exists, click Schedules in the left pane.
- On a Tableau Server with more than one site, click Manage all sites in the drop-down menu on the top of the left pane, and then click Schedules.
- On the Schedules page, click Select All.
- On the Actions menu, select Disable, and then click Disable in the resulting prompt.